AMP Solar Phase II Project

The systems each consist of solar photovoltaic generating facilities that use polycrystalline photovoltaic modules and central inverters. The modules are mounted on either a fixed tilt or tracker racking system. Each system is interconnected to the electric distribution system of a host participating community and is located on land within or near the geographic footprint of the host participant. 

There are 16 systems with a rated capacity of approximately 58.325 megawatts (MW) located in Delaware, Michigan, Ohio and Virginia. The systems have a rated capacity ranging from 0.25 MW to 20 MW. The first of the systems, located in Bowling Green, entered commercial operation in January 2017 (see more on the Bowling Green Solar Facility below). A list of the systems and the performance of each relative to P90 are set forth below in the following tables.

Systems

SiteRated Capacity (in MW)Commercial Operation Date
Bowling Green20.0001/24/2017
Marshallville0.7003/3/2017
Prospect0.2503/3/2017
Front Royal2.5005/8/2017
Orrville #20.9501/26/2018
Versailles1.7501/29/2018
Haskins0.7001/29/2018
Coldwater1.3052/1/2018
Jackson Center #21.6202/8/2018
Orrville #32.2503/3/2018
Smyrna1.1707/6/2018
Piqua Staunton1.7559/1/2018
Brewster1.8751/1/2019
Piqua Manier12.6257/17/2019
Wadsworth Seville Rd.6.2503/1/2020
Wadsworth Rittman Rd.2.6256/1/2020
Total58.325

Historical Performance of Systems

2024 Calendar Year

SiteActual Production (in MWh)P90 Projection (in MWh)Variance (%)Capacity Factor (%)Availability Factor (%)
Bowling Green38,82037,9312.322.199
Marshallville1,1011,0574.217.9100
Prospect394407(3)18.0100
Front Royal3,9594,076(2.9)18.097
Orrville #21,3111,322(0.8)15.7100
Versailles2,7082,5277.217.6100
Haskins8821,051(16.1)14.399
Coldwater2,0271,8907.217.7100
Jackson Center #22,8162,6436.519.8100
Orrville #33,3223,1804.516.8100
Smyrna1,8291,7186.417.8100
Piqua Staunton2,6402,791(5.4)17.1100
Brewster2,3562,371(0.6)14.3100
Piqua Manier22,01321,3733.019.80100
Wadsworth Seville Rd.10,56610,837(2.5)19.394
Wadsworth Rittman Rd.3,5553,669(3.1)15.498
Total/Average100,29998,8421.519.699
Includes data commencing with each system’s first full month of operation for systems entering commercial operation in 2024 and is through December 2024.

2023 Calendar Year

SiteActual Production (in MWh)P90 Projection (in MWh)Variance (%)Capacity Factor (%)Availability Factor (%)
Bowling Green39,64238,122422.6100
Marshallville1,1431,0637.618.7100
Prospect399409(2.4)18.2100
Front Royal4,2594,096419.4100
Orrville #21,3031,329(2)15.7100
Versailles2,6832,5395.717.5100
Haskins6481,057(38.7)10.599
Coldwater1,9941,900517.4100
Jackson Center #22,7902,657519.7100
Orrville #33,2993,1963.216.7100
Smyrna1,9111,72710.718.6100
Piqua Staunton2,6102,805(6.9)17100
Brewster2,2512,383(5.5)13.7100
Piqua Manier21,76321,4801.319.7100
Wadsworth Seville Rd.11,25710,8913.420.5100
Wadsworth Rittman Rd.3,6103,687(2.1)15.7100
Total/Average101,56499,3382.220>95
Includes data commencing with each system’s first full month of operation for systems entering commercial operation in 2023 and is through December 2023.

Bowling Green Solar Facility 

The Bowling Green Solar Facility, one of the largest solar installations in the state of Ohio, is a 20-MW installation located in Bowling Green and is part of the AMP Solar Phase II Project. 

NextEra Energy and their engineering, procurement and construction contractor, Blattner Energy, began construction in July 2016 and achieved mechanical completion in December 2016. The site achieved commercial operation in January 2017. 

The Bowling Green Solar Facility consists of 85,680 modules, twenty 1-MW inverters, ten 34.5-kilovolt (kV) transformers and spans 165.09 acres. The site also uses a tracker system that aids in maximizing production. A substation was also built on site that steps the voltage up from 34.5 kV to 69 kV.

Bowling Green Facility Facts

2017
Facility Went Online
The site produced its first megawatt-hours of sunshine-driven power in January
85,680 Solar Panels
The total number of solar modules installed at the site
175 Acres
The Bowling Green facility is one of the largest solar installations in Ohio

*Note that AMP, on behalf of its Members, sells all or a portion of the renewable energy certificates created by its renewable energy projects, power purchase agreements and joint ventures to help reduce its wholesale power costs.